RFQ Calls for Selling 20 Acres of Country Club Road Property to Housing Developers for $1.
The Montpelier City Council will vote this Wednesday, Oct. 22, on a document that could be sent out Thursday to housing developers who might be interested in the city’s Country Club Road (CCR) property. The city bought the 133-acre former golf course in 2022 for $3 million for recreation, housing, and conservation purposes.
The city is rushing to see if it can line up a developer to improve its chances of getting an $8 million state flood grant — if there is another round of state funding — to rebuild the CCR access road and install water and sewer lines to the property.
The state has already received a first round of applications for twice as much money as it has available and has said it will decide in early 2026 whether there will be a second round of funding.
The document to be sent to developers, titled “Request for Qualifications & Expressions of Interest,” states that the city “is open to any number of housing configurations and development build-out scenarios, with an eye to affordability and sustainability.”
The city’s goals are “to increase the availability of market and/or workforce housing in an area of the city that is outside of the floodplain,” the Request for Qualifications (RFQ) states.
The RFQ says the city is offering to sell all or part of 20 buildable acres for $1 and that the city would waive water and sewer hookup fees, offer discounted municipal permits, and potentially agree to municipal tax stabilization.
A council subcommittee, made up of councilors Sal Alfano, Ben Doyle, and Adrienne Gil, has been meeting with White + Burke employee Stephanie Clarke to draft the document that will be reviewed by the full council Wednesday.
The city recently signed a one-year brokerage contract with White + Burke to help recruit a developer or developers and to sell part or all of the property. The firm will be paid up to $50,000 on an hourly basis and, if it sells the property and development occurs, a commission of up to $300,000. It is not clear where the money to pay the commission would come from.
The process used to hire White + Burke and the late-night council vote to approve it has generated some controversy. Critics such as Steve Whitaker and Sandy Vitzthum have also continued to argue the city should not rush the project and should do more planning before it hires a developer.
Affordable Housing
The state’s flood recovery funds originated with the federal government and come with U.S. Department of Housing and Urban Development restrictions requiring that 70% of the state’s total grants benefit low and moderate income residents. In Washington County, that means households with incomes of $70,240 or less.
There had been some indication from the state that this meant any housing associated with the Country Club Road infrastructure project would have to meet the 70% requirement. But Montpelier Planning Director Mike Miller said he spoke with the state and that that is not the case.
“We specifically asked this question because if we do 300 housing units, [a 70% requirement] would mean we’d have to do 210 LMI [low- and moderate-income] housing units for only $8 million,” he told The Bridge. “That’s doesn’t make sense”
Miller said he was told the requirement is calculated by taking the cost of a housing unit and dividing it into the grant amount, then taking 70% of that. “We’re talking about a number in the range of 10 to 18 LMI units that would need to be created for a contribution of $8 million for infrastructure,” he said.
The city is also requesting a $3 million Catalyst grant from the Northern Border Regional Commission. If it wins that, plus gets $8 million from the state, the city will have a total of $11 million to spend on constructing access roads and water and sewer pipes to the property, raising U.S. Route 2, and building a new pump station.
Miller also responded to criticism of the city’s decision to hire consultant White + Burke to help with the RFQ and also serve as a broker for sale of the property without reaching out to any other firms.
“They have connections with the development community,” he said. “The development community is more comfortable working with the city because they know there is a real estate broker involved to make sure that the process [is] going efficiently. That’s what we’re paying for, that connection and that experience.”
Miller said he thinks the contract is a good deal. “It sounds like a lot of money, but at the same time, they’re doing a lot of work, and if they don’t succeed, they don’t get paid that much money,” he said.
Large Apartment Buildings or Small Single-Family Homes?
Montpelier architect Sandy Vitzthum has for some time been critical of the way the city has approached the Country Club Road project. She said the city should have done more planning and should be more specific about what it wants, rather than opening the property up to whatever developers propose.
For one thing, she noted, the city should do a financial analysis of how the project is going to affect the city. Vitzthum went on: “How much grand list is being added? What are the social benefits? What is the cost to the city? What other services will be needed? Will we need another ambulance or ladder truck? They’ve never done that analysis, which is bizarre.”
Vitzthum, who has her own proposal for developing for the property and is currently helping collect ideas from the public on what should be built there, noted that the RFQ does not talk about the building types the city wants or whether the housing should be homeownership or rentals.
Her view is that the most cost-efficient way to develop the property would be with very dense, small single-family homes and some small multifamily buildings. “We’re working on this with Plainfield, where we’ve gotten the total property values down to what’s actually affordable, as low as $130,000 to $150,000,” she said.
Vitzthum said small houses do not require elevators or fire suppression and there is no concrete or steel, she said, whereas large apartment buildings — which she says the city wants to include — require all those things and cost as much as $600,000 per unit to build, she said.
Subsidized apartment buildings do not add a lot of value to the city’s grand list, she added, because of state statutes that reduce their property tax liability. Vitzthum said rather than giving its $3 million investment to a developer, the city could sell off portions of the property to local developers who could build single-family homes and small multi-family properties. This might allow the city to refund the Recreation Fund, which contributed $1 million to the purchase of CCR; taxpayers are funding the remaining $2 million bond that allowed the city to purchase the property.
Miller’s view, and that of the subcommittee that drafted the RFQ, is that the city needs to move quickly to line up a developer so it will have a shot at the flood grant fund, if there is a second round. They say the city needs to see what developers think is possible, and they note the city will be able to negotiate with developers over what actually gets built.
Subcommittee member Ben Doyle believes that while planning is important, at this point the city needs to let the private market determine what is feasible at CCR. He wrote on Front Porch Forum that “entering an RFP process won’t lock us into anything. It will provide us with additional information and choices.”
If the RFQ is sent out Thursday as tentatively planned, developers will have until Nov. 18 to send in qualification proposals. From those who reply, the city plans to choose up to five who will be asked to submit more detailed proposals in a Request for Proposal (RFP). The RFP document will be sent out Dec. 11 with a deadline of Jan. 30, according to the RFQ.
Choosing a plan and working out the sale of the property would take some time, however. “We won’t break ground until 2027 at the earliest, probably 2028,” Miller said.
Another Montpelier resident who believes the city should do more planning before signing up a developer is Steve Whitaker. He has a number of other concerns, including that the city has not done enough research on the brownfields on the Country Club Road property or possible contamination in the building that houses Turtle Island, that the White + Burke contract vote was not warned, and that other firms should have been allowed to compete for the RFQ/RFP work.
Last week, Whitaker filed a complaint with the Vermont Real Estate Commission. It states that White + Burke told the city council that a brokerage agreement was legally required in order for the city to retain their services preparing an RFP.
“No Vermont statute or Board of Realtors rule requires such an agreement,” Whitaker asserted. He asked for a determination as to whether White + Burke’s representations were accurate and ethical.
Whitaker also alleged that the contract arrangement by which White + Burke will be paid a percentage of the increase in grand list value violates HUD procurement guidelines and could jeopardize eligibility for federal funding linked to the project.
David White, the principal in White+Burke, told The Bridge that Whitaker is incorrect, that if his firm is helping to offer a property for sale, such as through an RFP process, it does need a brokerage agreement. He pointed to Rule 2.1.b of the Vermont Real Estate Commission rules.
He also did not think HUD rules would apply to the sale of the property or his firm because the flood grant money would be for the infrastructure leading to the property, not the property itself.
White+ Burke has used brokerage agreements in the extensive work they have done with the city of Saint Albans starting over a decade ago, he noted. Since then, Saint Albans has been able to increase its grand list by 50%, he said. New projects have included a parking garage, a 100-room hotel, offices, both affordable and market-rate apartments, a senior housing project, and a mixed-use building, among other things.
“We are very busy right now, and had to seriously consider whether we wanted to take on the Country Club contract.” White said. “It would have been fine with us” if the city had sought other bidders for the contract through an RFP process, but “the city did not have time to do that and apply for the grant” and so it asked White+Burke to take the job on, he said.
Asked about his firm’s suggestion that the city offer to sell the property for $1, White noted that the RFQ only applies to about 20 acres of the property. He also said that the market for real estate development of affordable and middle-market housing is “broken,” necessitating a subsidy of some sort.
Other Vermont municipalities that have recently offered property to developers for $1 include St. Albans, Dorset and Bellows Falls, according to White. In Montpelier’s case, even if the property is offered for $1, “this is still going to be a difficult project to put together,” he said.
Correction
A story about Montpelier’s contract with White + Burke in the Oct. 15 printed issue of The Bridge erroneously reported that White + Burke had previously been paid $500,000 for planning work on the Country Club Road (CCR) property. In fact, it has only been paid about $67,000 to date for work on CCR. The Bridge regrets the error.
White + Burke previously worked on several other projects for the city, including the downtown TIF district, now disbanded, and the parking garage project. Since 2017, the total amount the city has paid the firm in billings and expenses is about $312,500, according to the firm.
White + Burke’s Actionable Plan for the CCR property, dated June 28, 2023, states that the “sunk costs” for the property include $500,000 in due diligence. Planning Director Mike Miller said that money is an estimate of the total soft costs that will be necessary to develop the property. To date, the city has spent about $256,000 in “soft costs,” Miller said, including payments to White + Burke, Black River Design, and VHB.